Twist Pin Line Throughput & Capacity Calculator
Project monthly finished-contact output of a ZEUEE 6-machine line. Bottleneck station is ZY04 cutting/welding (10–13 pcs/min).
11 pcs/min
22 days
85%
Projected Output
Monthly finished contacts—
Per shift-hour—
Daily output—
Annual capacity—
Assumes 8-hour shifts and ZY04 as the line bottleneck. Upstream stations (winding/braiding at 50 m/min, expansion at 15–17 pcs/min) hold headroom above this rate. Real ramp to target OEE typically takes one to two quarters.
Discuss Your Capacity Target with Our Engineers →WHY WE WRITE THIS
About ZEUEE Engineering Insights
ZEUEE shares technical guides based on real automation project experience. Since 2005, we have designed and manufactured non-standard automation equipment for connector assembly, wire harness production, robotic lines, vision inspection, and smart factory upgrades.
Founded in 2005
20,000 m² production base
120+ specialists
150+ R&D patents
ISO9001:2015 certified